Scottsdale Airport lines up a $1.86 million contract for two new exit taxiways, with about 65 overnight runway closures

Rows of white business jets parked on the paved ramp at Scottsdale Airport under a clear sky, with diners on a restaurant terrace at right and Camelback Mountain on the horizon
File photo (2021): Business jets parked on the ramp at Scottsdale Airport, seen from the terrace of the airport’s Volanti restaurant, with Camelback Mountain in the distance. Photo by Richard N Horne, CC BY-SA 4.0 (cropped). Source on Wikimedia Commons.

Scottsdale Airport is preparing to build two new exit taxiways off Runway 3-21, under a $1,861,523 construction contract that city aviation staff took to the Airport Advisory Commission on Wednesday, Nov. 18, according to the commission’s posted agenda packet.

The item asked the commission to recommend that the City Council adopt Resolution No. 13812, awarding contract No. 26IFB086 to J. Banicki Construction, Inc. for exit taxiways B9 and B15. The commission’s vote had not been posted on the city’s website as of Thursday morning; the contract still needs City Council approval.

What would be built

The new exits would link Runway 3-21 with Taxiway B along the northwest half of Taxiway B. According to the staff report, Phase 1 builds Taxiway B9 between existing taxiways B8 and B10, and Phase 2 builds Taxiway B15 between B13 and B16. Both phases include airfield lighting and electrical work, drainage improvements and new pavement markings. Staff wrote that the new exits “will enhance airfield capacity, efficiency and safety.”

Cost, timing and runway closures

The staff report says a Federal Aviation Administration grant would cover 95% of the construction cost ($1,768,446), an Arizona Department of Transportation grant 2.5% ($46,538), and the city’s Aviation Enterprise Fund the remaining 2.5% ($46,539). If the contract is awarded as scheduled, work would start in May 2027. About 65 overnight runway closures would be needed so crews can work safely within 200 feet of the runway centerline, the report says, and the phases were staged to keep disruption to aircraft operations low.

October traffic

The same packet’s October operations report counts 10,740 takeoffs and landings at the airport in October 2026, down 29% from 15,140 in October 2025. Year to date, operations were 128,550, down 6.5% from 137,570 a year earlier. The airport had 427 based aircraft, including 217 jets and 47 helicopters. The report does not give a reason for the October drop.

The agenda also listed Experience Scottsdale’s annual update, the election of a vice chair and three aeronautical business permit applications (hangar and shade leasing, aircraft sales and an aircraft charter service).

Source: City of Scottsdale, Airport Advisory Commission agenda and packet, Nov. 18, 2026 (PDF; Item 7 commission action report and October 2026 operations report); City of Scottsdale public meeting calendar; accessed Nov. 19, 2026

Neighborhoods: Airpark / Kierland